4 articles on WULF
-
TeraWulf secures Google credit backstop for Anthropic leases in Kentucky
The company also executed a definitive engineering, procurement and construction agreement with Fluor Enterprises for three data center buildings at the same campus.
-
TeraWulf raises contracted power at Muskie campus to 1 GW
TeraWulf said the second 500 MW phase's planned delivery moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule.
-
TeraWulf agrees to sell Abernathy stake for approximately $530 million
After the quarter ended, the company entered into a 20-year Anthropic lease for approximately 401 MW at its Justified Data Campus in Kentucky.
-
TeraWulf signs 20-year Anthropic lease and agrees to sell Abernathy stake
Consideration for the Abernathy sale is approximately $530 million, paid in three installments with the last on or before April 30, 2027.
How these are written
- The source: the company's own 8-K filing or press release, linked from every article. What the company says is attributed to the company.
- The checks: each article is written by GetSignal with AI and checked against its source before it is shown.
- The date: the day the company filed the 8-K or published the release.
- Not investment advice. An article reports what the company disclosed; it is not a view on the stock.