Applied Digital completes base-build commissioning of first 75 MW at Harwood
Within that phase, the first 25 MW data hall completed its integrated fit-out and reached Ready for Service on schedule.
GetSignal
Applied Digital said on November 24, 2026 that it has completed base-build commissioning for the first 75 MW of its initial 150 MW data center building at Polaris Forge 2 in Harwood, North Dakota.
Key facts
- Location
- Harwood, North Dakota
- Campus
- Polaris Forge 2
- Commissioned capacity
- First 75 MW of initial 150 MW data center building
- Ready for Service
- First 25 MW data hall
Source: The company's release on GlobeNewswire, November 24, 2026.
Written by GetSignal with AI from the company's press release. How we make news
Not investment advice.
More company news
Applied Digital first, then the newest- Applied Digital closes $300 million senior secured bridge facility
APLD · Applied Digital · Company release · Nov 23, 2026
- Applied Digital reports fiscal first quarter revenue of $341.9 million, up 322%
APLD · Applied Digital · Form 8-K · Oct 7, 2026
- Applied Digital reports fiscal fourth-quarter revenue of $258.7 million
APLD · Applied Digital · Form 8-K · Jul 27, 2026
- The PNC Financial Services Group names Brian LeBlanc chief economist
PNC · PNC Financial Services Group · Company release · Nov 24, 2026
- Thermo Fisher Scientific gets FDA clearance for expanded EXENT Analyser use
TMO · Thermo Fisher Scientific · Company release · Nov 24, 2026
- Raytheon awarded Navy contract to advance submarine-launched nuclear cruise missile
RTX · Company release · Nov 24, 2026