Duke Energy says North Carolina regulators advanced its 2025 Carolinas resource plan

Duke Energy said some projects will need additional project-specific review and approval, with continued opportunity for public input, before moving forward.

GetSignal 

Share
Download on the App StoreGet it on Google Play

Free on iOS and Android

The North Carolina Utilities Commission issued an order on Duke Energy's 2025 Carolinas Resource Plan, and Duke Energy issued a statement on it on November 17, 2026. Duke Energy said the plan shows how it will meet rapid growth in the Carolinas while keeping affordability in focus. Kendal Bowman, Duke Energy's North Carolina president, said the plan reflects an all-of-the-above approach that includes natural gas, solar, batteries and new nuclear.

The order adds 2,300 MW of solar beyond the commission's 2022 and 2024 orders, for 8,100 MW total by 2034, and 2,700 MW of battery storage beyond those orders, for 5,400 MW total by 2034. It also moves forward 2,720 MW of additional combined cycle capacity and 1,111 MW of additional combustion turbines, and Duke Energy said regulators also approved the planned combustion turbines where the former Buck coal plant once stood.

The order approved continued development work supporting either small modular reactors or large light water reactors. It authorized the company to develop and submit amendments to the Nuclear Regulatory Commission for two AP1000 units at the W.S. Lee site in Cherokee County, S.C., and revisions to the combined license application for two AP1000 units at the Shearon Harris site in Wake County, N.C.

Duke Energy said some of the projects are already under construction, while others need project-specific review and approval first, with continued opportunity for public input. Duke Energy said other projects will require additional project-specific review and approval, with continued opportunity for public input, before moving forward. Construction is underway at the Person County Energy Complex and at a second battery storage facility replacing the retired Allen Plant. Duke Energy said construction will begin in 2027 at the approved Anderson Natural Gas Project.

Duke Energy said the plan's projected cost to customers over the next decade was reduced by nearly half compared with the plan approved by regulators in 2024. It also said combining Duke Energy Carolinas and Duke Energy Progress, effective Jan. 1, is projected to save customers $2.3 billion from 2027 to 2040.

Key facts

Planned solar additions in resource plan
2,300 MW, 8,100 MW total by 2034
Planned battery storage additions in resource plan
2,700 MW, 5,400 MW total by 2034
Projected savings from combining utilities
$2.3 billion, 2027 to 2040
DOE grant funding
More than $110 million

All DUK news

Source: The company's release on PR Newswire, November 17, 2026.

Written by GetSignal with AI from the company's press release. How we make news

Not investment advice.