Company newsForm 8-K and release
WhiteFiber completes $60 million purchase of two North Carolina industrial sites
WhiteFiber said the sites are expected to provide a minimum of 60 megawatts combined, subject to confirmation, with up to 198 megawatts possible within seven years after closing.
GetSignal
WhiteFiber completed on October 28, 2026 its acquisition of two industrial properties in Yadkin County, North Carolina, for $60 million in cash. The buyer was Enovum Data Centers Corp., a Canadian subsidiary wholly owned by WhiteFiber, and the seller was Unifi Manufacturing, Inc., a wholly owned subsidiary of Unifi, Inc. The sites, designated NC-2 and NC-3, are about 55 miles from WhiteFiber's NC-1 campus in Madison, North Carolina.
The properties include about 120 acres of land and 500,000 square feet of warehouse space. WhiteFiber said each property is expected to be served with a minimum of 30 megawatts, or 60 megawatts combined, subject to the confirmation process set out in the agreement with the seller. It said up to 69 more megawatts per property could become available within seven years after closing, a combined maximum of up to 198 megawatts, subject to the confirmation process set out in the agreement with the seller. Each figure is subject to the purchase agreement's confirmation process.
The seller retained the right to occupy portions of the properties after closing, under occupancy and partial leaseback arrangements. WhiteFiber said these arrangements are expected to offset a portion of property carrying costs. An earnest money deposit of $2.25 million, held in escrow, was applied to the purchase price at closing. WhiteFiber said it intends to retrofit the properties into data center campuses, building on its regional development experience.
WhiteFiber said it has received non-binding letters of intent from a broad range of prospective customers for NC-2, NC-3 and NC-1 expansion capacity, including proposals from investment-grade counterparties. WhiteFiber said it is targeting initial ready-for-service capacity at NC-2 and NC-3 in late 2027, subject to customary development conditions. Chief Executive Officer Sam Tabar said the company is encouraged by the breadth of customer demand.
At NC-1, switchgear-related commissioning issues interrupted service and billing for the first 20 MW IT data hall, and about 35 of the contracted 40 MW IT deployment is now operational. WhiteFiber said it continues to advance financing for NC-1 with a prospective lending group. WhiteFiber said there can be no assurance that the financing will be completed. WhiteFiber said it will report third-quarter 2026 financial results on November 10, 2026.
Key facts
- Purchase price
- $60 million in cash
- Closing date
- October 28, 2026
- Earnest money applied
- $2.25 million
- Expected initial capacity
- Minimum of 60 megawatts combined, subject to confirmation process
- Potential capacity
- Up to 198 megawatts across the properties within seven years after closing, subject to confirmation
- Initial ready-for-service target
- Late 2027, subject to customary development conditions
Sources: Form 8-K filed November 3, 2026, and the company's release on PR Newswire, November 3, 2026.
Written by GetSignal with AI from the company's press release. How we make news
Not investment advice.
More company news
WhiteFiber, Inc. Ordinary Shares first, then the newest- WhiteFiber subsidiaries enter $300 million term loan credit agreement
WYFI · WhiteFiber, Inc. Ordinary Shares · Form 8-K · Nov 10, 2026
- Western Digital stockholders elect nine directors at annual meeting
WDC · Western Digital · Form 8-K · Nov 20, 2026
- Ares Capital subsidiary amends BNP Paribas funding facility
ARCC · Ares Capital · Form 8-K · Nov 20, 2026
- FACT II Acquisition extends business combination deadline to November 25, 2027
FACT · FACT II Acquisition · Form 8-K · Nov 20, 2026