Earnings call briefSecond-quarter 2026

TeraWulf estimates WULF Compute cost at approximately $9.1 million per megawatt

TeraWulf said the figure is within its original range of $8 million to $10 million per megawatt, and above the approximately $8.6 million financed in October 2025.

GetSignal TeraWulf WULF

On its second-quarter call, TeraWulf said the updated estimate reflects electrical labor constraints and evolving customer equipment and operating requirements.

CFO Patrick Fleury said that, after the FluidStack lease amendments and TeraWulf's additional capital contributions, the project's pro forma capitalization is expected to be approximately 32% equity and 68% debt, compared with approximately 26% equity and 74% debt at the time of financing.

Quotes from the call

“We currently estimate total project costs at approximately $9.1 million per megawatt within that original guidance range and modestly above the approximately $8.6 million per megawatt financed in October 2025.”

Patrick Fleury, CFO

Key facts from the call

Estimated WULF Compute project cost per megawatt
approximately $9.1 million
Original range per critical IT megawatt
$8 million to $10 million
Cost per megawatt financed in October 2025
approximately $8.6 million

All WULF call briefs

Source: TeraWulf's second-quarter 2026 earnings call, August 5, 2026.

Written by GetSignal with AI from the company's earnings call.

Not investment advice.

More earnings call briefs

  1. Constellation Energy expects nuclear uprate costs of about $4.3 billion

    CEG  Constellation Energy  Q3 2026 call 

  2. Brookfield Asset Management now sees 2026 earnings modestly below early view

    BAM  Brookfield Asset Management  Q3 2026 call 

All earnings call briefs

Follow TeraWulf on GetSignal

Its earnings call briefs, filings, insider trades and company news in one feed. Free on iPhone and Android.

Download on the App Store Get it on Google Play