Soluna Holdings plans to fund large AI builds mainly with project debt

For a 100-megawatt build-out, Chief Financial Officer Michael Picchi said the remaining 20% to 30% would come from Soluna contributions or third-party project equity.

GetSignal Soluna Holdings SLNH

Soluna Holdings said on its second-quarter call that a 100-megawatt build-out, which it estimates at $1.2 billion to $1.3 billion, would target 70% to 80% project-level debt, likely high-yield notes sized against contracted tenant cash flows under the lease.

Picchi said debt and equity formation would be expected within 8 to 12 weeks after a signed lease is announced.

Quotes from the call

“For a 100-megawatt build-out, which we estimate at $1.2 billion to $1.3 billion, we would target 70% to 80% project level debt, likely high-yield notes sized against the contracted tenant cash flows under the lease, with the remaining 20% to 30% from Soluna contributions or third-party project equity.”

Michael Picchi, Chief Financial Officer

Key facts from the call

Estimated cost of 100-megawatt build-out
$1.2 billion to $1.3 billion
Target project-level debt
70% to 80%
Remaining funding
20% to 30% from Soluna contributions or third-party project equity

All SLNH call briefs

Source: Soluna Holdings' second-quarter 2026 earnings call, August 13, 2026.

Written by GetSignal with AI from the company's earnings call.

Not investment advice.

More earnings call briefs

  1. Constellation Energy expects nuclear uprate costs of about $4.3 billion

    CEG  Constellation Energy  Q3 2026 call 

  2. Brookfield Asset Management now sees 2026 earnings modestly below early view

    BAM  Brookfield Asset Management  Q3 2026 call 

All earnings call briefs

Follow Soluna Holdings on GetSignal

Its earnings call briefs, filings, insider trades and company news in one feed. Free on iPhone and Android.

Download on the App Store Get it on Google Play